Relining in 2001 of BF 4 of Dunkirk

Published online by Cambridge University Press:  25 October 2002

Get access

Abstract

In July 2001, Dunkirk blast furnace 4 achieved a 13 years and 9 months long campaign with a 41.7 millions tons hot metal cumulative output. The relining works had been scheduled within a 65 to 75 days period for a total cost over 150 millions Euros. The objectives of the next campaign are : a daily production over 10,800 tons, a blast furnace life over 20 years without any intermediate repair, a significant improvement of the working conditions and a major reduction of the environmental impact.

Type
Research Article
Copyright
© La Revue de Métallurgie, 2002

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)