7 - Delivering Healthcare Infrastructure and Services through Public–Private Partnerships: The Lesotho Case

from Part I - Mitigating Institutional Voids by Design

Published online by Cambridge University Press:  14 November 2019

Nuno Gil
Affiliation:
University of Manchester
Anne Stafford
Affiliation:
University of Manchester
Innocent Musonda
Affiliation:
University of Johannesburg
Get access

Summary

Many governments in Africa are establishing public–private partnerships (PPPs) to provide healthcare infrastructure and services. We know very little about how healthcare PPPs are planned and implemented in Africa, and even less about the associated outcomes. This paper begins to address this gap through a detailed case study of an innovative, ambitious and complex partnership contract in Maseru, Lesotho. The scheme has been labelled ‘the future of healthcare delivery on the African continent’ and encompasses the design, build, partial financing and full operation of a new hospital facility alongside a wide range of core clinical services. This chapter draws on documentary data to evaluate the main features of the contract, the procurement process and monitoring arrangements and the outcomes in terms of benefits and costs. A key finding is that payments to the private operator are far higher than was expected pre-contractually, and have become a major source of budgetary uncertainty, as well as a demanding call on government’s healthcare resources. We conclude that successful social infrastructure PPPs in Africa will require considerable investments in contract management skills, strong budgeting institutions and mechanisms, and enhanced (and more independent) scrutiny of plans and forecasts of financial impacts.

Type
Chapter
Information
Duality by Design
The Global Race to Build Africa's Infrastructure
, pp. 203 - 226
Publisher: Cambridge University Press
Print publication year: 2019

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)

References

Acerete, B., Stafford, A. and Stapleton, P. (2012). New global health care PPP developments – A critique of the success story. Public Money & Management, 32 (4), 311314.Google Scholar
Barlow, J. and Kӧberle-Gaiser, M. (2009). Delivering innovation in hospital construction: Contracts and collaboration in the UK’s Private Finance Initiative hospitals program. California Management Review, 51: 126143.Google Scholar
Colla, P., Hellowell, M., Vecchi, V. and Gatti, S. (2015). Determinants of the cost of capital for privately financed hospital projects in the UK. Health Policy, 119(11): 14421449.Google Scholar
Downs, S., Montagu, D., da Rita, P., Brashers, E. and Feachem, R. (2013). Health system innovation in Lesotho. San Francisco, CA: UCSF and PricewaterhouseCoopers.Google Scholar
Dudkin, G. and Välilä, T. (2005). Transaction costs in public-private partnerships: A first look at the evidence. EIB Economic and Financial Report 2005/03. Luxembourg: European Investment Bank.Google Scholar
Farquharson, F., de Mastle, C. T. and Yescombe, E. (2011). How to engage with the private sector in public-private partnerships in emerging markets. Washington, DC: World Bank Group.CrossRefGoogle Scholar
Flyvbjerg, B., Holm, M. and Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279–95.Google Scholar
Fӧlscher, A. (2007). Budget methods and practices. In Shah, A. (Ed.), Budgeting and budgetary institutions. Washington, DC: The World Bank.Google Scholar
Guasch, J. L., Benitez, D., Portabales, I. and Flor, L. (2014). The renegotiation of PPP contracts: An overview of its recent evolution in Latin America. International Transport Forum Discussion Papers, no. 2014–18, George Mason University, Washington, DC.Google Scholar
Government of Lesotho (2007). New referral hospital public private partnership, request for best and final offers, 30 October 2007. Maseru, Lesotho: Government of Lesotho.Google Scholar
Government of Lesotho (2009). New referral hospital public private partnership – Financial model (v6.01). Maseru, Lesotho: Government of Lesotho.Google Scholar
Grout, P. (2003). Public and private sector discount rates in public-private partnerships. Economic Journal, 113, C63C68.CrossRefGoogle Scholar
Hellowell, M. (2013). PFI redux? Assessing a new model for financing hospitals. Health Policy, 113 (1–2), 7785.Google Scholar
Hellowell, M. and Vecchi, V. (2012). An evaluation of the projected returns to investors on 10 PFI projects commissioned by the National Health Service. Financial Accountability and Management, 28(1), 77100.Google Scholar
Hellowell, M., Vecchi, V. and Caselli, S. (2015). Return of the state? An appraisal of policies to enhance access to credit for infrastructure-based PPPs. Public Money & Management, 35(1), 7178.CrossRefGoogle Scholar
International Finance Corporation (2010). Lesotho: New public-private partnership set to boost access to health care for the poor. Washington, DC: World Bank Group.Google Scholar
Iossa, E. and Martimort, D. (2012). Risk allocation and the costs and benefits of public-private partnerships. The RAND Journal of Economics, 43(3): 442474.Google Scholar
Irving, J. and Manroth, A. (2009). Local sources of financing for infrastructure in Africa. Washington, DC: World Bank.Google Scholar
Koppenjan, J. F. M. and Enserink, B. (2009). Public–private partnerships in urban infrastructures: Reconciling private sector participation and sustainability. Public Administration Review, 69: 284296. http://dx.doi.org/10.1111/j.1540-6210.2008.01974.xGoogle Scholar
Lohmann, C. and Rötzel, P. G. (2014) Opportunistic behavior in renegotiations between public-private partnerships and government institutions: data on public-private partnerships of the German armed forces. International Public Management Journal, 17(3), 387410.Google Scholar
Lonsdale, C. (2005). Contractual uncertainty, power and public contracting. Journal of Public Policy, 25(2), 219240.CrossRefGoogle Scholar
Lonsdale, C. and Watson, G. (2007). Managing contracts under the private finance initiative. Policy and Politics, 35(4), 683700.Google Scholar
Marriot, A. (2014). A dangerous diversion: Will the IFC’s flagship health PPP bankrupt Lesotho’s Ministry of Health? London: Oxfam GB.Google Scholar
McKee, M., Edwards, N. and Atun, R. (2006). Public–private partnerships for hospitals, Bulletin of the World Health Organization, 84, 890896.Google Scholar
Montagu, D. and Harding, A. (2012). A zebra or a painted horse? Are hospital PPPs infrastructure partnerships with stripes or a separate species? World Hospitals and Health Services, 48(2): 1519.Google ScholarPubMed
Monteiro, R. (2013). Implementing a framework for managing fiscal commitments from Public Private Partnerships. Washington DC: The Financial and Private Sector Development Network.Google Scholar
National Audit Office (2015). The choice of finance for capital investment. Available at: www.nao.org.uk/report/the-choice-of-finance-for-capital-investment/ (Accessed 19 March 2015).Google Scholar
Netcare Limited (2012). Transcript from the results presentation for the six months ended 31 March 2012. Available at: www.netcare.co.za/Portals/0/Investor%20Relations/Financial%20Results/2012%20-%20Interim%20results/Transcript%20of%20presentation%20results.pdf?ver=2017-05-15-140106-787 (Accessed 24 November 2014).Google Scholar
Qu, Y. and Loosemore, M. (2013). A meta-analysis of opportunistic behaviour in public-private partnerships: manifestations and antecedents. In Smith, S. D. and Ahiaga-Dagbui, D. D. (Eds.), Procs 29th Annual ARCOM Conference, 2–4 September Association of Researchers in Construction Management, Reading, UK, pp. 415424.Google Scholar
Reiss, A. (2005). Is the PPP model applicable across sectors? EIB Papers, 10 (2): 1030.Google Scholar
Ross, T. and Yan, J. (2015). Efficiency vs. flexibility in public-private partnerships. Journal of Comparative Policy Analysis, 17(5): 448466.Google Scholar
Shaoul, J., Stafford, A. and Stapleton, P. (2011). NHS capital investment and PFI: from central responsibility to local affordability. Financial Accountability & Management, 27: 117.Google Scholar
UNICEF and World Bank. (2017). Lesotho: Public health sector expenditure review 2017. Washington DC: The World Bank.Google Scholar
Vian, T., McIntosh, N., Grabowski, A. and Brooks, B. (2013). Endline study for Queen ’Mamohato Hospital Public Private Partnership (PPP): Draft final report. Boston, MA: Boston University.Google Scholar
Vian, T., McIntosh, N., Grabowski, A., Limakatso Nkabane-Nkholongo, E. and Jack, B. W. (2015). Hospital public–private partnerships in low resource settings: Perceptions of how the Lesotho PPP transformed management systems and performance. Health Systems & Reform, 1(2), 155166.Google Scholar
Williamson, O. (1985). The economic institutions of capitalism. New York, NY: The Free Press.Google Scholar
Williamson, O. (1990). Transaction cost economics and organisation theory. In Williamson, O. (Ed.), Organisation theory: From Chester Barnard to the present and beyond. New York, NY: Oxford University Press.Google Scholar
World Bank. (2013). Implementation completion and results report on a grant in the amount of $6.25 million to the Kingdom of Lesotho for a new hospital PPP project (p104403). Washington DC: World Bank Group.Google Scholar
Yescombe, E. R. (2017). Public private partnerships in sub-Saharan Africa: Case studies for policymakers. Dar es Salaam, Tanzania: Uongozi Institute. Available at: www.africaportal.org/publications/public-private-partnerships-in-sub-saharan-africa-case-studies-for-policymakers-2017/ (Accessed 1 July 2017).Google Scholar

Save book to Kindle

To save this book to your Kindle, first ensure coreplatform@cambridge.org is added to your Approved Personal Document E-mail List under your Personal Document Settings on the Manage Your Content and Devices page of your Amazon account. Then enter the ‘name’ part of your Kindle email address below. Find out more about saving to your Kindle.

Note you can select to save to either the @free.kindle.com or @kindle.com variations. ‘@free.kindle.com’ emails are free but can only be saved to your device when it is connected to wi-fi. ‘@kindle.com’ emails can be delivered even when you are not connected to wi-fi, but note that service fees apply.

Find out more about the Kindle Personal Document Service.

Available formats
×

Save book to Dropbox

To save content items to your account, please confirm that you agree to abide by our usage policies. If this is the first time you use this feature, you will be asked to authorise Cambridge Core to connect with your account. Find out more about saving content to Dropbox.

Available formats
×

Save book to Google Drive

To save content items to your account, please confirm that you agree to abide by our usage policies. If this is the first time you use this feature, you will be asked to authorise Cambridge Core to connect with your account. Find out more about saving content to Google Drive.

Available formats
×