Skip to main content Accessibility help
×
Hostname: page-component-77c89778f8-cnmwb Total loading time: 0 Render date: 2024-07-17T23:21:22.992Z Has data issue: false hasContentIssue false

2 - A calamitous history of cost overrun

Published online by Cambridge University Press:  05 July 2014

Bent Flyvbjerg
Affiliation:
Aalborg University, Denmark
Nils Bruzelius
Affiliation:
Stockholms Universitet
Werner Rothengatter
Affiliation:
Universität Fridericiana Karlsruhe, Germany
Get access

Summary

In this and the following chapters we review the experience from a large number of megaprojects, including the Channel tunnel and the links across Great Belt and Øresund, all three multibillion-dollar projects. Although we subject these projects to critical scrutiny, our objective is not to criticise them, even where they have underperformed, but to learn constructively from experience by identifying lessons that may prove useful in improving future decisions regarding megaprojects. Given the large amounts of money spent on major transport infrastructure projects, it is remarkable how little data and research are available that would help answer the two basic questions: (i) whether such projects have the intended effects; and (ii) how the actual viability of such projects compares to projected viability. Therefore, in addition to transport projects, we have found it pertinent to review data and research from other types of infrastructure project and to compare experience from these projects with experience from the transport sector. In this manner, we will review data from several hundred large projects. In this chapter we focus on the costs of megaprojects. In Chapters 3 and 4 we consider the demand for, and viability of, such project.

A first step in reducing cost overrun is to acknowledge that a substantial risk for overrun exists and cannot be completely eliminated; but it can be moderated.

The problem of cost overrun

Cost overruns in major transport infrastructure projects are widespread.

Type
Chapter
Information
Megaprojects and Risk
An Anatomy of Ambition
, pp. 11 - 21
Publisher: Cambridge University Press
Print publication year: 2003

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)

Save book to Kindle

To save this book to your Kindle, first ensure coreplatform@cambridge.org is added to your Approved Personal Document E-mail List under your Personal Document Settings on the Manage Your Content and Devices page of your Amazon account. Then enter the ‘name’ part of your Kindle email address below. Find out more about saving to your Kindle.

Note you can select to save to either the @free.kindle.com or @kindle.com variations. ‘@free.kindle.com’ emails are free but can only be saved to your device when it is connected to wi-fi. ‘@kindle.com’ emails can be delivered even when you are not connected to wi-fi, but note that service fees apply.

Find out more about the Kindle Personal Document Service.

Available formats
×

Save book to Dropbox

To save content items to your account, please confirm that you agree to abide by our usage policies. If this is the first time you use this feature, you will be asked to authorise Cambridge Core to connect with your account. Find out more about saving content to Dropbox.

Available formats
×

Save book to Google Drive

To save content items to your account, please confirm that you agree to abide by our usage policies. If this is the first time you use this feature, you will be asked to authorise Cambridge Core to connect with your account. Find out more about saving content to Google Drive.

Available formats
×